WeRead Powered by ReaderPub
Concrete Construction: Methods and Costs cover

Concrete Construction: Methods and Costs

Chapter 63: CHAPTER XIV.
Open in WeRead

Explore more books like this:

About This Book

A practical treatise on performing and costing concrete work, presenting methods for selecting and preparing cement, sand, and aggregates; proportioning and measuring mixtures; and making, transporting, and placing concrete by hand and by machine. It covers underwater deposition and subaqueous grouting, rubble and asphaltic concretes, procedures for freezing weather, surface finishing techniques, formwork design and removal, and pile and pier construction. Each chapter pairs procedural guidance with equipment options and analyzed cost data to inform planning and execution of concrete projects.

Total.Per cu. yd.
2 men carrying cement$3.00$0.012
6 men shoveling sand9.000.036
17 men shoveling stone25.000.100
11 men wheeling stone16.000.064
2 men at stone and sand bins3.000.012
2 men opening cement bags3.000.012
1 man dumping hopper1.500.006
1 man dumping mixer1.500.006
1 man cleaning chute, mixer, etc.1.500.006
1 motorman or engineer3.000.012
——————
  Total labor mixing$66.50$0.266
8 men pushing 2 cars12.000.048
2 men cleaning track, etc.3.000.012
7 men spading concrete10.500.042
——————
    Total labor transporting, placing$ 25.50$0.102
1 foreman5.000.020
Electricity estimated7.000.028
——————
    Total general$ 12.00$0.048
        Grand total$104.00$0.416

It will be noted that the cost of shoveling and wheeling the broken stone amounts to 16.4 cts. per cu. yd., or nearly 40 per cent. of the total cost of mixing and placing. The cost of spading the concrete is also high for a sloppy mixture, but is probably accounted for by the fact that the concrete had to be spaded so as to have 2 or 3 ins. of clear mortar next the forms. The forms used in constructing the wall are shown by Figs. 110 and 111. They were made in panels 51 ft. long and a locomotive crane was used to shift the panels. This crane worked handling forms only a small part of the time, but a form gang of 10 carpenters was kept busy all of the time moving and reassembling. Assuming the work of the crane to amount to $5 per day and the wages of the carpenter gang to amount to $25, we get a cost of 12 cts. per cubic yard of concrete for shifting forms. It should be noted carefully that the costs given for this work do not include cost of materials, interest on plant, superintendence and other items.

Fig. 110.—End View of Forms for Retaining Wall, New York Central Terminal Work.

WALL FOR RAILWAY YARD.—For building a retaining wall 7 ft. high, forms were made and placed by a carpenter and helper at $8 per M., wages being 35 cts. and 20 cts. an hour, respectively. Concrete materials were dumped from wagons alongside the mixing board. Ramming was unusually thorough. Foreman expense was high, due to small number in gang; 2 cu. yds. were laid per hour by the gang.

Fig. 111.—Corner Detail of Retaining Wall Forms, New York Central Terminal Work.
Per day.Per cu. yd.
7 mixers, 15 cts. per hour$10.50$0.53
2 rammers, 15 cts. per hour3.000.15
1 foreman 30 cts. per hr., 1 waterboy 5 cts.3.500.17
——————
    Total labor$17.00$0.85

The total cost was as follows per cubic yard:

Per cu. yd.
0.8 bbls. Portland cement, at $2$1.60
Sand0.30
Gravel0.70
Labor mixing and placing0.85
Lumber for forms, at $16 per M.0.56
Labor on forms, at $8 per M.0.28
———
    Total, per cubic yard$4.29

The sheathing plank for the forms was 2-in. hemlock.

CONCRETE FOOTING FOR RUBBLE MASONRY RETAINING WALL.—In constructing a footing for a retaining wall at Grand Rapids, Mich., a 1-2½-5 natural cement concrete was used. It was found that 1 cu. yd. of concrete was equivalent to 29.8 cu. ft. of material composed of 3.6 cu. ft. or 1.1 bbls. of cement, 8.4 cu. ft. or 2.7 bbls. of sand and 17.8 cu. ft. or 5.5 bbl. of broken stone. The labor cost of 15.5 cu. yds. of concrete was as follows:

Item.Total.Per cu. yd.
Foreman, 14 hours at 40 cts.$ 5.60$0.3613
Foreman, 20 hours at 22.5 cts.4.500.2903
Laborers, 49 hours at 12.5 cts.6.110.3942
Mason, 2 hours at 35 cts.0.700.0451
———————
    Total labor$16.91$1.0909

All material was furnished by the railway company, the contractor furnishing labor only; his contract price for this was $1 per cu. yd.

TRACK ELEVATION, ALLEGHENY, PA.—The wall was 6,100 ft. long and 75 per cent. was on curves. The first wall built had a top width of 2½ ft. and a bottom width of 0.4 the height with the back on a smooth batter. Later the back was stepped and last the wall was proportioned as follows: Calling the height from top of foundation to under coping, then width of base was 0.45 (h + 3), the top measuring 2½ ft. The back was arranged in steps 24 ins., 30 ins. and 36 ins. high, and the thickness of wall at each step was, calling h equal to height of step from base, 0.45 (h + 3). Several forms of expansion joints were tried. The first was tarred paper extending through the wall every 50 ft.; the second was ½-in. boards running through the wall every 50 ft.; the third was ½-in. board extending 2 ft. into the wall, with a ¼-in. cove at the angles, every 25 ft. The third construction gave perfect satisfaction.

A 1-2-5 natural cement and a 1-3-6 Portland cement concrete mixed fairly wet were used. The concrete was laid in 8-in. courses and faced with a 1-2 mortar. The forms were 2-in. white pine faced and jack planed on the edges; upon removal of the forms board marks and other defects were removed and a wash of neat cement was applied. One contractor used hand mixing. The sand and gravel were measured in wheelbarrows and wheeled onto the platform; the sand and cement were spread in thin layers, one over the other, and thoroughly mixed dry; the gravel was then spread over the mixture, the whole was shoveled into barrows or the pit again shoveled into place and rammed. The other contractor used a cubical mixer. A charging box holding 1¼ cu. yds. and graduated to show the correct proportions of sand and gravel was filled by shoveling; cement was placed on top and the box hoisted and dumped into the mixer. A barrel holding the correct amount of water was emptied into the mixer which was turned 10 or 15 times and discharged into cars. The costs of mixing by hand and by machine were as follows:

  Hand mixing.Total.Per cu. yd.
½ foreman at $3$ 1.50$0.025
3 men wheeling barrows at $1.504.500.075
10 men wheeling materials at $1.5015.000.250
3 men mixing sand and gravel at $1.504.500.075
6 men mixing concrete at $1.509.000.150
1 man sprinkling at $1.501.500.025
——————
    Total$36.00$0.600

The output of the hand mixing gang was 60 cu. yds. per day.

  Machine mixing.Total.Per cu. yd.
1 foreman at $3.50$ 3.50$0.035
1 stationary engineer at $33.000.030
½ foreman at $1.750.870.009
15 men loading charging bucket at $1.5022.500.225
2 men dumping charging bucket at $1.753.500.035
2 tagmen at $2, ½ time2.000.020
1 man at trap at $2, ½ time1.000.010
——————
    Total$36.37$0.364

The output of the cubical mixer was 100 cu. yds. per day.

The costs of placing concrete in the forms above the foundation by hand below 12 ft., and by cars and derricks any height, were as follows:

  By hand (barrows) below 12 ft.Total.Per cu. yd.
4 men loading concrete at $1.50$ 6.00$0.100
1 foreman ½ time at $31.500.025
10 men wheeling at $1.5015.000.250
1 man scraping barrows at $1.501.500.025
2 men placing concrete at $1.503.000.050
1 man placing mortar face at $1.501.500.025
2 men mixing and carrying mortar at $1.503.000.050
——————
    Total$31.50$0.525
  By cars and derricks—
1 horse and driver at $3$ 3.00$0.030
2 men dumping concrete ½ time at $1.501.500.015
1 fireman ½ time at $1.750.880.009
3 tagmen at $1.504.500.045
8 men placing and ramming conc. at $1.5012.000.120
2 men mixing mortar at $1.503.000.030
2 men placing mortar at $1.503.000.030
2 men carrying mortar at $1.503.000.030
1 foreman at $33.000.030
1 stationary engineer at $33.000.030
2 men attending hook at $1.503.000.030
——————
    Total$39.88$0.399

The costs of placing concrete in the foundations were as follows:

  By hand—Total.Per cu. yd.
1 foreman ½ time at $3$ 1.50$0.025
4 men shoveling concrete at $1.506.000.100
1 man placing concrete at $1.501.500.025
1 man ramming concrete at $1.501.500.025
——————
    Total$10.50$0.175
  By machine—
1 horse and driver at $3$ 3.00$0.030
3 men pushing and unloading car at $1.504.500.045
5 men placing and ramming at $1.507.500.075
1 foreman at $33.000.030
2 men dumping mixer at $1.503.000.030
——————
    Total$21.00$0.210

COST OF RETAINING WALL.—The following figures of the cost of a concrete retaining wall are given by C. C. Williams:

Cost of Material.
  Kind and amount of material—Unit Price.Cost.
Stone, 441 tons$ .70$308.70
Sand, 182.5 yds..55100.37
Cement, 536 bbls..85453.60
———
    Total$862.67
Lumber ¾ value$205.33
Wheelbarrows, ¾ value, 6 at $3.5015.75
———
    Total$221.08
  Excavation—
Labor, 4,002 hours at 15 cts.$600.30
Carts, 800 hours at 12½ cts.100.00
Foreman, 460 hours at 35 cts.171.00
Waterboy, 240 hours at 10 cts.24.00
———
    Total$895.30
  Concrete—
Labor, 2,398 hours at 15 cts.$359.70
Foreman, 224 hours at 35 cts.77.40
———
    Total$437.10
  Handling material—
Unloading cars, 380 hours at 15 cts.$ 57.00
Foreman, 40 hours at 35 cts.14.00
———
    Total$ 71.00
  Forms—
Carpenters, 997 hours at 22½ cts.$224.33
  Work to support bridge—
Carpenters, 542 hours at 22½ cts.$121.95
Labor, 458 hours at 15 cts.68.70
———
    Total$190.65
  Superintendence and office—
Superintendent, 30 hours at 50 cts.$15.00
Office20.00
————
     Total$35.00
————
        Grand total$2,937.13
    Proportional costs—
  Item.Cost.Cost Per Yard of Concrete.Per Cent. of Total Cost.
Concrete materials$ 862.67$2.0246.7
Laying concrete437.101.0323.4
Lumber205.33.4811.3
Building forms224.33.5312.3
Handling material71.00.1703.8
Wheelbarrows15.75.0401.0
Supt., etc.35.00.0701.5
—————————
    Total$1,851.18$4.34100.00
Work on bridge190.65
Excavation895.30
————
$2,937.13

CHAPTER XIV.

METHODS AND COST OF CONSTRUCTING CONCRETE FOUNDATIONS FOR PAVEMENTS.

Contractor's skill or want of skill in systematizing and managing labor counts as high in street work as in any class of concrete construction. As previously demonstrated, the cost of mixing is a very small portion of the labor cost of concrete in place; the costs of getting the materials to the mixer and the mixed concrete to the work are the big items, and in street work the opportunity for increasing the cost of these items through mismanagement is magnified by the large area of operations involved per cubic yard of concrete placed. One cubic yard of concrete makes 6 sq. yds. of 6-in. pavement foundations and 100 cu. yds. of concrete make a 6-in. foundation for 300 ft. of 30-ft. street, while 4 to 5 cu. yds. will build 100 ft. of ordinary curb and gutter. Thus the haulage per cubic yard is considerable at best, and lack of plan in distributing stock piles and handling the concrete can easily result in such increased haulage expenses as to change a possible profit into a certain loss. A little thought and skill in planning street work pays a good profit.

MIXTURES EMPLOYED.—A comparatively lean concrete will serve for pavement foundations; mixtures of 1-4-8 Portland cement or 1-2-5 natural cement are amply good and it is folly, ordinarily, to employ richer mixtures. Until recently, natural cement has been used almost exclusively; a 1-2-5 natural cement mixture requires about 1.15 bbls. of cement per cubic yard of concrete. A 1-4-8 Portland cement mixture requires about 0.7 bbl. of cement per cubic yard. In the opinion of the authors a considerably leaner mixture of Portland concrete is sufficiently good when it is well mixed in machine mixers—for a 6-in., foundation 0.5 bbl. per cu. yd. The mixtures actually employed are proportioned about as stated and their cost, or that of any other common mixture, may easily be computed from Tables XII and XIII, giving for different mixtures the quantities of cement, sand and stone per cubic yard of concrete; the product of these quantities and the local prices of materials in the stock piles gives the cost. When the concrete is mixed by hand the ordinary labor cost of foundations is 0.4 to 0.5 of a 10-hour day's wages per cubic yard of concrete; occasionally it may be as low as 0.3 of a day's wages where two mixing gangs are worked side by side under different foremen and with an exacting contractor. Data for machine mixing are too few to permit a similar general statement for machine work, but in one case coming under the authors' observation, the cost figured out to a little less than 0.2 of a day's wages per cubic yard.

DISTRIBUTION OF STOCK PILES.—Assuming a 30-ft. street and a 1-3-5 concrete laid 6 ins. thick, the quantities of concrete materials required per lineal foot of street are: Cement 0.60 bbl., sand 0.27 cu. yd., stone 0.44 cu. yd. The stock piles should be so distributed that each supplies enough materials for a section of foundation reaching half way to the next adjacent stock pile on each side, and they should not contain more or less material, otherwise a surplus remains to be cleaned up or a deficiency to be supplied by borrowing from another pile. A little care will ensure the proper distribution and it is well paid for in money saved by not rehandling surplus or borrowed materials. For a given mixture and a given width and thickness of foundation, the sizes of the stock piles are determined by their distance apart and this will depend upon whether hand or machine mixing is employed and upon the means adopted for hauling the raw materials and the mixed concrete. It is worth while always in stock piles of any size, to lay a flooring of plank particularly under the stone pile; if dumped directly on the ground it costs half as much again to handle stone. Current practice warrants everything from a continuous bank, to piles from 1,000 to 1,500 ft. apart, in the spacing of stock piles.

HINTS ON HAND MIXING.—All but a small percentage of the concrete annually laid in street work is hand mixed. The authors are confident that this condition will disappear as contractors learn more of the advantages of machine mixing, but it prevails at present. The general economics of hand mixing are discussed in Chapter II; in street work as before stated, the big items of labor cost are the costs of handling materials and the data in Chapter II on these processes deserve special attention. It is particularly worth noting that it is seldom economical to handle materials in shovels where carrying is necessary; it is a common thing in street work to see an attempt to get the stock piles so close to the mixing board that the material can be handled with shovels, and this is nearly always an economic error. Street work is readily measured; in fact, its progress can be seen at a glance, and advantage can often be taken of this fact to profit by the rivalry of separate gangs. The authors have known of the labor costs being reduced as much as 25 per cent., due to pitting one gang against another where each could see the progress made by the other.

METHODS OF MACHINE MIXING.—Concrete mixers have been slow to replace handwork in laying pavement foundations. In explanation of this fact it is asserted: (1) That frequent shifting of the mixer causes too much lost time, and (2) that the principal item of labor cost in street work is the conveying of materials to and from the mixer, and this item is the same whether hand or machine mixing be employed. The records of machine mixer work given elsewhere in this chapter go far, in the opinion of the authors, toward disproving the accuracy of both assertions. If the machine used and the methods of work employed are adapted to the conditions of street work, machine mixing can be employed to decided advantage.

A continuous and large output is demanded in a mixer for street work; the perfection of the mixing is within limits a minor consideration. This at once admits for consideration types of mixers whose product is classed as unsuitable for reinforced concrete work, and also admits of speeding up the output of the better types to a point beyond that at which they turn out their most perfect product. Keeping these facts in mind either of the following two systems of work may be employed: (1) Traction plants which travel with the work and deposit concrete in place, or so nearly in place that little shoveling is necessary; (2) portable plants which are set up at wide intervals along the work and which discharge the concrete into carts or dump wagons which distribute it to the work.

The secret of economic work with plants of the class cited first is the distribution of the stock piles so as practically to eliminate haulage from stock pile to mixer. The mixer backs away from the work, its discharge end being toward the work and its charging end away from it. Then deposit the materials so as to form a continuous stock pile along the center of the street; the mixer moving backward from the completed foundation keeps close to the materials and if the latter are uniformly distributed in the pile the great bulk of the charging is done by shoveling direct into the charging bucket. The point to be watched here is that the shovelers do not have to carry the materials; separate stock piles within moderate hauling distance by wheelbarrows are a far more economic arrangement than a continuous pile so irregularly distributed that much of the material has to be carried even a few paces in shovels.

Economic work with plants of the second class depends upon efficient and adequate means of hauling the mixed concrete to the work. The plant should not be shifted oftener than once in 1,000 to 2,000 ft., or, say, four city blocks. This does away with the possibility of wheelbarrow haulage; large capacity hand or horse carts must be employed. With 6 cu. ft. hand carts, such as the Ransome cart, a haul of 500 ft. each way from the mixer is possible and with horse carts, such as the Briggs, this economic distance is increased to 1,000 ft. each way from the mixer. The mixer must be close to the stock pile and it will pay to make use of improved charging devices. A 6-in. foundation for 2,000 ft. of 30-ft. street calls for 667 cu. yds. of concrete, and if both sides are curbed at the same time, 100 cu. yds. more are added, or 767 cu. yds. in all; where intersecting streets are to be paved in both directions from the mixer plant these amounts are doubled. A very small saving per cubic yard due to mechanical handling of the materials to the mixer amounts to the interest on a considerable investment in such plant. A point that should not be forgotten is that carts such as those named above spread the concrete in dumping so that little or no shoveling is required.

FOUNDATION FOR STONE BLOCK PAVEMENT, NEW YORK, N. Y.—Mr. G. W. Tillson, in "Street Pavements and Paving Materials," p. 204, gives the following data on the cost of granite block pavement in New York City in 1899. The day was 10 hours long:

  Concrete gang—Per day.Per sq. yd.Per cu. yd.
1 foreman$ 3.00$0.0125$0.075
8 mixers on two boards, at $1.2510.000.04160.250
4 wheeling stone and sand, at $1.25.5.000.02080.125
1 carrying cement and supplying water, at $1.251.250.00510.031
1 ramming, at $1.251.250.00510.031
—————————
    Total, 240 sq. yds. (40 cu. yds.).$20.50$0.0851$0.512

The concrete was shoveled direct from the mixing boards to place.

Cost 1-2-4 concrete—Per cu. yd.
1⅓ bbls. natural cement, at $0.90$1.20
0.95 cu. yd. stone, at $1.251.19
0.37 cu. yd. sand, at $1.000.37
Labor0.51
——
$3.27

In laying 5,167 sq. yds. of granite block pavement on one job in New York City in 1905, the authors' records show that one laborer mixed and laid 1.3 cu. yds. of concrete per day in a 6-in. foundation; this is a very small output. The work was done by contract and the labor cost was as follows:

  Item.Total.Per sq. yd.Per cu. yd.
28½ days foreman at $3.50$ 99.75$0.0193$0.118
399 days laborers at $1.75698.250.13510.826
—————————
$798.00$0.1544$0.944

The average day's wages was $1.86, so that the labor cost was about 0.5 of a day's wages per cubic yard of concrete.

FOUNDATION FOR PAVEMENT, NEW ORLEANS. LA.—Mr. Alfred E. Harley states that in laying concrete foundations for street pavement in New Orleans, a day's work, in running three mixing boards, covering the full width of the street, averaged 900 sq. yds., 6 ins. thick, or 150 cu. yds., with a gang of 40 men. With wages assumed to be 15 cts. per hour the labor cost was:

  Cts. per cu. yd.
6 men wheeling broken stone6
3 men wheeling sand3
1 man wheeling cement1
2 men opening cement2
7 men dry mixing7
8 men taking concrete off8
3 men tamping3
3 men grading concrete3
1 man attending run planks1
3 water boys1
2 extra men and 1 foreman4
    Total labor cost39 cts.

FOUNDATIONS FOR STREET PAVEMENT, TORONTO, CANADA.—The following cost of a concrete base for pavements at Toronto has been abstracted from a report (1892) of the City Engineer, Mr. Granville C. Cunningham. The concrete was 1-2½-7½ Portland; 2,430 cu. yds. were laid, the thickness being 6 ins., at the following cost per cubic yard:

0.77 bbl. cement, at $2.78$2.14
0.76 cu. yd. stone, at $1.911.45
0.27 cu. yd. sand and gravel, at $0.800.22
Labor (15 cts. per hr)1.03
——
      Total$4.84

Judging by the low percentage of stone in so lean a mixture as the above, the concrete was not fully 6 ins. thick as assumed by Mr. Cunningham. Note that the labor cost was 1½ to 2 times what it would have been under a good contractor.

MISCELLANEOUS EXAMPLES OF PAVEMENT FOUNDATION WORK.—The following records of pavement foundation work are taken from the note and time books of one of the authors:

Case 1.—Laying 6-in. pavement foundation; stone delivered and dumped upon 2-in. plank laid to receive it. Sand and stone were dumped along the street, so that the haul in wheelbarrows to mixing board Was about 40 ft. Two gangs of men worked under separate foremen, and each gang averaged 4.5 cu. yds. concrete per hour. The labor cost was as follows for 45 cu. yds. per gang:

Per day.Per cu. yd.
4 men filling barrows with stone and sand ready for the mixers, wages 15 cts. per hour$6.00$0.13
10 men, wheeling, mixing and shoveling to place (3 or 4 steps), wages 15 cts. per hour15.000.33
2 men ramming, wages 15 cts. per hour3.000.07
1 foreman at 30 cts. per hour and 1 water boy, 5 cts3.500.08
————
    Total$27.50$0.61

Case II.—Sometimes it is desirable to know every minute detail cost, for which purpose the following is given:

Per cu. yd.
Day's labor.Cost.
3 men loading stones into barrows$0.06$0.09
1 man loading sand into barrows0.020.03
2 men ramming0.040.06
1 foreman and 1 water boy equivalent to0.0350.05
Wheeling sand and cement to mixing board0.020.03
Wheeling stone to mixing board0.0260.04
9 men mixing mortar0.0130.02
Mixing stone and mortar0.0490.07
Placing concrete (walking 15 ft.)0.0720.11
—————
    Total$0.335$0.50

In one respect this is not a perfectly fair example (although it represents ordinary practice), for the mortar was only turned over once in mixing instead of three times, and the stone was turned only twice instead of three or four times. Water was used in great abundance, and by its puddling action probably secured a very fair mixture of cement and sand, and in that way secured a better mixture than would be expected from the small amount of labor expended in actual mixing. About 9 cts. more per cu. yd. spent in mixing would have secured a perfect concrete without trusting to the water.

Case III.—Two gangs (34 men) working under separate foremen averaged 600 sq. yds., or 100 cu. yds. of concrete per 10-hour day for a season. This is equivalent to 3 cu. yds. per man per day. The stone and sand were wheeled to the mixing board in barrows, mixed and shoveled to place. Each gang was organized as follows:

Per day.Per cu. yd.
4 men loading barrows$ 6.00$0.12
9 men mixing and placing13.500.27
2 men tamping3.000.06
1 foreman2.500.05
—————
    Total$25.00$0.50

These men worked with great rapidity. The above cost of 50 cts. per cu. yd. is about as low as any contractor can reasonably expect to mix and place concrete by hand in pavement work.

Case IV.—Two gangs of men, 34 in all, working side by side on separate mixing boards, averaged 720 sq. yds., or 120 cu. yds., per 10-hour day. Each gang was organized as follows:

Per day.Per cu. yd.
6 men loading and wheeling$ 9.00$0.15
8 men mixing and placing12.000.20
2 men tamping3.000.05
1 foreman3.000.05
—————
    Total$27.00$0.45

Instead of shoveling the concrete from the mixing board into place, the mixers loaded it into barrows and wheeled it to place. The men worked with great rapidity.

Mr. Irving E. Howe gives the cost of a 6-in. foundation of 1-3-5 natural cement at Minneapolis, Minn., in 1897, as $2.80 per cu. yd., or $0.467 per sq. yd. Cement cost 76 cts. per barrel and stone and sand cost delivered $1.15 and 30 cts. respectively. Mixers received $1.75 per day.

Mr. Niles Meriwether gives the cost of materials and labor for an 8-in. foundation constructed by day labor (probably colored) at Memphis, Tenn., in 1893, as follows:

Per sq. yd.
Natural cement at $0.74 per bbl$0.195
Sand at $1.25 per cu. yd0.075
Stone at $1.87 per cu. yd0.355
Labor mixing and placing0.155
——
    Total$0.780

Labor was paid $1.25 to $1.50 per 8-hour day and 1.16 bbls. of cement were used per cubic yard of concrete. The cost of materials, as will be noted, was high and the labor seems to have been inefficient.

FOUNDATIONS FOR BRICK PAVEMENT, CHAMPAIGN, ILL.—The concrete foundation for a brick pavement constructed in 1903 was 6 ins. thick; the concrete used was composed of 1 part natural cement, 3 parts of sand and gravel, and 3 parts of broken stone. All the materials were mixed with shovels, and were thrown into place from the board upon which the mixing was done. The material was brought to the steel mixing board in wheelbarrows from piles where it had been placed in the middle of the street, the length of haul being usually from 30 to 60 ft. The foundation was 6 ins. thick and it cost as follows for materials and labor:

Cost per cu. yd.
1.2 bbls. cement, at $0.50$0.600
0.6 cu. yd. sand and gravel, at $10.600
0.6 cu. yd. broken stone, at $1.400.840
6 men turning with shovels, at $20.080
4 men throwing into place, at $20.053
2 men handling cement, at $1.750.023
1 man wetting with hose, at $1.750.012
2 men tamping, at $1.750.023
1 man leveling, at $1.750.012
6 men wheeling stone, at $1.750.070
4 men wheeling gravel, at $1.750.047
1 foreman, at $40.027
———
$2.387

This is practically 40 cts. per sq. yd., or $2.40 per cu. yd. of concrete for materials and labor. It is evident from the above quantities that a cement barrel was assumed to hold about 4.5 cu. ft., hence the cement was measured loose in making the 1-3-3 concrete. The accuracy of the quantities given is open to serious doubt. It will also be noted that the labor cost of making and placing the concrete was only 35 cts. per cu. yd., wages being nearly $1.85 per day. This is so remarkably low that some mistake would seem to have been made in the measurement of the work. The authors do not hesitate to say that no gang of men ever made any considerable amount of concrete by hand at the rate of 5.75 cu. yds. per man per day.