APPENDIX.
ACTUAL COST OF STEAM SHOVEL WORK.
(From an article in Engineering News, June 9, 1888, we take the following particulars of reports on the actual cost of steam shovel work, and these reports show how variable is the cost of excavating, depending, as it does, upon delay, unavoidable on every line of railway, upon the weather, character of the material, length of haul, and many other conditions. When conditions are favorable as to material, prompt and short hauling, with no delays, the results show a very large increase in the output, and often a decrease in cost.—Ed. Eng. News.)
From a report of the General Roadmaster of the New York Central & Hudson River R. R. of work done by two shovels on the Eastern and Western divisions, we find the largest day's work for one shovel at Yost's pit was 174 cars, the average for the month of August being 121 cars per day and for July 116 cars per day. It could have made a larger average than this with twenty more cars, as the trains making long runs could not keep cars in the pit. The largest day's work at Bergen pit with one machine was 156 carloads, the June average being 117 cars and the July 116 cars per day, and for two weeks in August 134 cars per day. At this pit they came in contact with cement, hard pan, and very coarse material. At Yost's pit they have loaded 10,511 cars in four months up to Aug. 1. Figuring these at 9 yds. per car, which is low, makes 94,599 yds. The cost of delivering on roadbed was $5,261.25, or about 5½ cts. per yd. The average cost for handling by men loading and unloading is 14 cts. per yd.
The report on a machine working in New Mexico on the Atchison, Topeka & Santa Fe R. R. says: "In cemented gravel, we find no difficulty, under favorable circumstances, in loading 75 to 100 cars per day, at a cost not to exceed 10 cts. per cu. yd."
The engineer of the Cleveland, Mt. Vernon & Delaware R. R. gives some statements as to the cost and amount of some excavating work done under his direction. This shovel worked about 5½ months in stiff clay, as follows:
- March loaded 1154 cars, worked 24 days.
- July loaded 955 cars, worked 24 days.
- Aug. loaded 1157 cars, worked 22 days.
- Sept. loaded 1556 cars, worked 23 days.
- Oct. loaded 1552 cars, worked 23 days.
- Nov. loaded 539 cars, worked 12 days.
Total, 6,915 cars, 41,490 cu. yds. Greatest number of cars loaded in a single day, 97. Shovel supposed to work ten hours a day, but did not average more than 6½ hours on account of waiting for cars. Carloads average 6 cu. yds. per car. Average cost of loading, 3 cts. per cu. yd., including expense of all men, shovel, oil, waste, etc. Loaded, hauled material, and unloaded at a distance of ten miles from pit, at 10 cts. per yd., including all costs, shovel, use of cars, engines and crews. A 20-mile haul on this road cost 15 cts. per yd., and a 30-mile haul about 20 cts. per yd., while on some roads a 30-mile haul costs over 75 cts. per yd., depending on the frequency of trains.
The following report from the superintendent of the Sioux City & Pacific Ry. gives the operations of a shovel for nine months working in a yellow clay bank from 30 to 40 ft. in length, and with a one-mile haul: "The total number of cars loaded was 31,420 in 209 days, giving an average of 150¾ cars per day. The greatest number of cars loaded in one day was 275, with an average of 6 cu. yds. per car. The average cost of loading per cu. yd. is 6½ cts., including expense of all men about shovel, and shifting of shovel track. Average cost of unloading with one-mile haul, 7.8 cts., including wages of all men with trains and engines, use of cars and locomotives, with all supplies and repairs of same, making a total cost of 14.3 cts. per cu. yd. or 85.8 cts. per car delivered on track."
A report showing the largest amount of work, with the most complete detail as to the expense of operation was furnished by the resident engineer of the Missouri Valley & Blair Railway & Bridge Co., contractors for the Chicago & Northwestern Ry. bridge across the Missouri River at Missouri Valley, Ia., the material excavated being used in the approaches to the bridge. The work, a tabulated statement of which is given in Table IV., was done under the most favorable circumstances, with but few delays, and with but one locomotive, as the cars ran down the hill themselves while being loaded, the locomotive being employed to haul the empty cars back; the haul was short and a round trip was made in 30 minutes. The report shows that during the work of six months the average number of cars loaded per day was 205, including delays and movings, and that the average cost per cu. yd. was 7 cts., which, as shown, included labor of loading, moving shovel about once a month, moving track to suit, dynamite for caving bank, repairs of shovel, fuel, oil, waste, wages of watchman, rent of cars and locomotives, labor of engineers, firemen and wipers, labor, conductors and brakemen, and, in fact, absolutely everything connected in any way with filling the embankment.
TABLE IV.
Work Done by Steam Excavator in Six Months at Missouri Valley, Ia.
| Repairs to locomotive, shovel and cars; material | $457.14 |
| Repairs to locomotive, shovel and cars; labor | 211.80 |
| Supplies for shovel | 1,760.00 |
| Rent of locomotive and cars | 1,404.75 |
| Supplies for locomotive | 1,781.52 |
| Wages of locomotive attendants | 1,508.37 |
| Wages of all other employees | 10,680.01 |
| ————— | |
| Total cost | $17,803.59 |
| Cars loaded | 32,141 |
| Cost per car | 55.38 cts. |
| Cost per cubic yard | 7 cts. |
| Hours worked by gang | 2,325 |
| Hours worked by shovel | 1,926 |
The report of the Roadmasters' Association for 1885 gives the cost of steam shovel work as follows:
| Railway. | Work. | Cost per yd. | |
| Baltimore & Ohio | Including everything, haul 5 to 25 miles | 8.1 cts. | |
| Michigan Central | Loading | 4.5 cts. | |
| Michigan Central | Hauling, 30 miles, labor only | 4.0 cts. | |
| N. Y., P., & O. | Loading | 7.0 cts. | |
| Central Iowa | Loading | 4.75 | cts. |
| "" | Unloading | 1.9 | cts. |
| "" | Engine service | 3.1 | cts. |
| —— | |||
| "" | Total | 9.75 | cts. |
The detailed statement given in Table V. was prepared by Mr. E. A. Hill, Acting Chief Engineer of the Indianapolis, Decatur & Springfield R. R., and is a record of work done under the supervision of Mr. A. J. Diddle, Roadmaster. It shows marked economy and gives an excellent idea of how the expenses are apportioned. The Otis type of excavator was used, which cuts 24 ft. wide and to a depth of 4 ft. below the track. The banks were about 15 ft. high, the average haul 4,000 ft. Twelve flat cars constituted a train. By a special cable arrangement the time of plowing off, ordinarily requiring about 15 minutes, was reduced to 5 or 6 minutes.
TABLE V.
Steam Shovel Work; Indianapolis, Decatur & Springfield R. R.
| Sangamon River Trestle. |
Montezuma Gravel Pit. |
Sangamon River Trestle. |
Guion Trestle. |
Nichol's Hollow Trestle. | |
| 1885. | 1886. | 1886. | 1887. | 1887. | |
| Total number of days | 54 | 186 | 48 | 108 | 51 |
| Number of working days | 46 | 115 | 38 | 85 | 40 |
| Days idle besides Sundays | 0 | 45 | 3 | 7 | 4 |
| Material handled | light clay. | gravel. | light clay. | light clay. | light clay. |
| Average height of bank | 10 ft. | 12 ft. | 10 ft. | 10 ft. | 12 ft. |
| Total No. cars loaded | 2,899 | 8,631 | 2,771 | 5,254 | 2,528 |
| Greatest No. load. per day | 94 | 124 | 90 | 80 | 75 |
| Least No. cars load. per day | 22 | 16 | 50 | 30 | 15 |
| Average No. loaded per day | 63 | 75 | 73 | 61.8 | 63.2 |
| Average length of haul | 1 mile. | 9 miles. | 1 mile. | 2 miles. | ¾ mile. |
| Grade, shovel to dump, p. c. | -1.00 | varying. | -1.00 | -1.00 | -1.00 |
| Tons coal used, shov. & eng. | 141 | 853 | 99 | 170 | 65 |
| No. car loads per ton coal. | 20.5 | 10 | 28 | 30.9 | 38.9 |
Cost of Work Per Car Load.
| Sangamon River Trestle. |
Montezuma Gravel Pit. |
Sangamon River Trestle. |
Guion Trestle. |
Nichol's Hollow Trestle. | |
| 1885. | 1886. | 1886. | 1887. | 1887. | |
| Cts. | Cts. | Cts. | Cts. | Cts. | |
| Foreman at $125 per month | 8.86 | 9.67 | 8.00 | 9.01 | 9.88 |
| Cranesman, $2 to $2.50 day | 5.35 | 5.62 | 4.80 | 3.54 | 5.57 |
| Fireman (shovel) $1.50 day | 2.88 | 3.37 | 2.87 | 2.90 | 3.27 |
| Laborers (4) $1.25 per day | 7.86 | 9.92 | 8.77 | 9.80 | 9.80 |
| Watchman at $1 per day | 2.07 | 1.96 | 1.88 | 2.50 | 2.25 |
| Total shovel crew | 27.02 | 30.54 | 26.32 | 27.75 | 30.77 |
| Engr. and fireman (engine) | 12.00 | 14.50 | 7.44 | 11.00 | 13.10 |
| Trainmen (conductor, $2.50; brakemen, $1.50) | 5.97 | 14.60 | 5.74 | 5.25 | 5.77 |
| Total train crew | 17.97 | 29.10 | 13.18 | 16.25 | 18.87 |
| Helpers distrb. earth, $1.10 | .... | 1.74 | .... | .... | 2.72 |
| Sec. men (track work), $1.10 | 0.81 | 1.88 | 1.38 | 1.45 | .... |
| Bridge carpenters (repairs to plant), $2.50 | 0.15 | 1.58 | 0.16 | 1.04 | 2.08 |
| Sec. men (reprs plant), $1.10 | .... | 0.62 | .... | .... | .... |
| Shop bills (repairs to plant) | 1.69 | 10.90 | 1.27 | 10.60 | 1.67 |
| Total repairs to plant | 1.84 | 13.10 | 1.43 | 11.64 | 1.67 |
| Coal from $1.25 to $1.41 ton | 6.31 | 13.30 | 4.47 | 4.31 | 3.28 |
| Oil, waste, etc. | 0.52 | 1.55 | 0.75 | 0.86 | 0.36 |
| Total supplies | 6.83 | 14.85 | 5.22 | 5.17 | 3.64 |
| —— | —— | —— | —— | —— | |
| Grand total per car load | 54.47 | 91.19 | 47.53 | 62.26 | 59.75 |
| —— | —— | —— | —— | —— | |
| Cost, cu. yd., 8 yds. per car | 6.43 | 11.40 | 5.94 | 7.79 | 7.47 |
| Add " " for interest on cost of plant | 1.00 | 1.00 | 1.00 | 1.00 | 1.00 |
| —— | —— | —— | —— | —— | |
| Cost per cu. yd., includ. int. | 7.43 | 12.40 | 6.94 | 8.79 | 8.47 |