An important modification in the form of the tuyeres has been introduced with the object of furnishing more effectively the necessary large volume of air at suitable pressure, and of increasing the efficiency at the tuyere zone. Instead of supplying the air to the furnace at a number of separated points, it was felt that the closer these could be brought together the better. A narrow slot all round the furnace for air admission has been held to be the most perfect method, but hitherto it has been thought impracticable, though a recent form of furnace (not at this plant) has been devised on this system. The improvement here has been the use of slotted tuyeres, 12 inches long by 4 inches wide, each of which replaces two of the older tuyeres of 3¼ inches diameter. These have proved very successful, the furnace thus equipped handling a much larger tonnage, and it has been decided to adopt the new form on all the furnaces.
Charging is by side-dumping V-shaped cars, and great care is taken in the handling and distribution of the charges. The furnaces are fitted with tops of special design, and with elaborate dust-catching devices which have been the subject of long and numerous experiments; the special purpose being to allow the taking off of the gases below the feed-floor, and to reduce the height of the superstructure to the smallest possible proportions, so as to prevent excessive dilution (by air) of the furnace gases, which are used for sulphuric acid manufacture. The furnace tops were originally of the standard form—brick walls supported by steel frame-work. It was, however, necessary to damper down the flues in order to obtain sufficient pressure to force the gases through the Glover towers, and the heat has caused the steel work to warp badly. A low top was tried, using a brick-lined flue at the end for taking off the gases below the feed-floor. This was found to be good for charge-dumping and general convenience, but it allowed the escape of too much smoke and flames, which greatly interfered with the furnace manipulation. In consequence the tubular top was used, gradually raised until a suitable height was reached. This form has been described on p. 140.
The present practice at Copperhill is to smelt the ore pyritically for a 9 to 10 per cent. matte, passing the products through the 16-foot settlers which are now lined with siliceous copper ore, then tapping the matte into ladles which empty it into beds of flue-dust. Alternate layers of matte and dust are thus incorporated, and yield a porous material convenient for the concentrating pyritic smelt which follows. This re-concentration is now conducted in a furnace narrowed to 44 inches, which has been found specially well suited for the work; the furnace runs fast, smelting sometimes over 800 tons of charge per day. The system of working is that of hard driving so long as the furnace smelts rapidly. As soon as it slows down, the furnace is tapped out and started afresh. The re-concentrating charge contains some limestone in order to reduce the copper losses in the slag, the saving effected by this feature being equivalent to 2 lbs. of copper per ton of ore smelted. The resulting matte is bessemerised.
The furnace gases are utilised for sulphuric acid manufacture, the acid plant being the largest in the world, with an ultimate capacity of 400 tons per day.
Ducktown.—It was at the Ducktown Company’s smelter that the first work on pyritic smelting in the district was carried out, and the successful development of the process generally, owes much to Freeland’s early pioneer work, the remarkable results of which led Parke-Channing to adopt the process at the Copperhill plant.
TABLE XI.—Typical Charging Tables at Pyritic Smelter.
| B.F. No. 3—Night Shift. Typical Green Ore Charges. |
|||||
|---|---|---|---|---|---|
| I. | II. | III. | IV. | ||
| Lbs. | Lbs. | Lbs. | Lbs. | ||
| Coke, | 180 | 240 | 240 | 400 | .. |
| Ore A., | 5,000 | .. | .. | .. | .. |
| Ore B., | .. | 5,000 | .. | .. | .. |
| Ore C., | .. | .. | 5,000 | .. | .. |
| Slag, | .. | .. | .. | 4,000 | .. |
| Lime rock, | .. | .. | .. | .. | .. |
| Green ore (low grade) matte, | .. | .. | .. | .. | .. |
| Flue-dust, | .. | .. | .. | .. | .. |
| Quartz (for flux), | 950 | .. | .. | .. | .. |
| Total weight of charge, | 6,130 | 5,240 | 5,240 | 4,400 | .. |
| Hours of Charging— | No. of Charges |
No. of Charges |
No. of Charges |
No. of Charges |
Total per Hr |
| 6–7, | 2 | 2 | .. | .. | 4 |
| 7–8, | 2 | .. | 2 | 2 | 6 |
| 8–9, | 2 | 2 | .. | .. | 4 |
| 9–10, | 2, 2 | .. | 2, 2 | .. | 8 |
| 10–11, | .. | 2 | .. | 2 | 4 |
| 11–12, | 2 | .. | 2 | .. | 4 |
| 12–1, | 2, 2 | 2 | .. | .. | 6 |
| 1–2, | 2 | .. | 2 | 2 | 6 |
| 2–3, | 2 | 2 | .. | .. | 4 |
| 3–4, | 2 | .. | 2 | .. | 4 |
| 4–5, | 2 | .. | .. | 2 | 4 |
| 5–6, | 2, 2 | 2 | 2 | .. | 8 |
| Total No. of charges daily, | 28 | 12 | 14 | 8 | 62 |
| B.F. No. 5—Day Shift. Typical Concentrating Charges. |
||||
|---|---|---|---|---|
| I. | II. | III. | ||
| Lbs. | Lbs. | Lbs. | ||
| Coke, | 150 | 400 | extra 700 | .. |
| Ore A., | .. | .. | .. | .. |
| Ore B., | .. | .. | .. | .. |
| Ore C., | .. | .. | .. | .. |
| Slag, | .. | 4,000 | .. | .. |
| Lime rock, | 700 | .. | .. | .. |
| Green ore (low grade) matte, | 3,500 | .. | .. | .. |
| Flue-dust, | .. | .. | .. | .. |
| Quartz (for flux), | 1,050 | .. | .. | .. |
| Total weight of charge, | 5,400 | 4,400 | 700 | .. |
| Hours of Charging— | No. of Charges |
No. of Charges |
Total per Hr |
|
| 6–7, | 2, 2, 2, 2, 2, 2, 2 | .. | .. | 14 |
| 7–8, | 2, 2, 2, 2 | 2 | .. | 10 |
| 8–9, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 9–10, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 10–11, | 2, 2 | 2, 2, 2, 2 | .. | 12 |
| 11–12, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 12–1, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 1–2, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 2–3, | 2, 2, 2 | 2, 2 | .. | 10 |
| 3–4, | 2, 2, 2, 2, 2, 2 | .. | .. | 12 |
| 4–5, | 2, 2, 2, 2, 2 | .. | .. | 10 |
| 5–6, | 2, 2, 2 | 2, 2, 2, 2 | .. | 14 |
| Total No. of charges daily, | 120 | 12 | .. | 132 |
It will be observed that the concentrating furnace works twice as quickly as the green ore matting furnace, and hence one furnace only is required for the concentration of the matte product from two of the matting furnaces.
The Isabella smelter comprises two furnaces of moderate size, 17 feet by 3 feet 4 inches at the tuyeres, having a joint capacity of 500 to 600 tons daily. The furnaces are about 9 feet high, and are water-cooled. Air at only 20 to 30 ozs. pressure is supplied through 3-inch tuyeres. The smelting scheme is somewhat analogous to that adopted at Copperhill, the first smelting producing a 20 per cent. copper matte from the 2 per cent. ore, whilst the re-concentration results in a converter-grade matte assaying 50 per cent. The coke proportions are somewhat similar to those used at Copperhill, being 5·0 per cent. for the first smelting, and 3·5 per cent. for the second. The furnace management at this small plant is exceedingly efficient, and the campaigns are long, it being claimed that the furnace operations have never had to be completely stopped on account of crusting or gobbing. This is held to be due to the results of special care in feeding and charge distribution, the ingenious Freeland charger already described being used. The charge is kept low (6 to 8 feet above the tuyeres), and is evenly red hot all through. The slags assay 35 to 36 per cent. silica, 38·8 per cent. iron, and 8·0 per cent. lime—with moderate copper losses. The annual output is equivalent to about 3,000 tons of metallic copper. An acid-making plant is also attached to these works.
The Manufacture of Sulphuric Acid from Pyritic Furnace Gases.—Modern legislative requirements make severe demands upon the managements of smelter-works where sulphury ores are dealt with, by reason of the disastrous effects of the sulphurous gases upon the conditions of life generally in the vicinity. In other cases, litigation by neighbouring farmers and others impose restrictions on the amount and character of the gases which the smelters are allowed to emit from their furnace stacks. So serious has the problem become that several smelters have had to cease operations altogether, others have been mulcted in enormous costs by law suits, by claims for compensation, or by the installation of plant and processes which they have been compelled to adopt for dealing with the gases. These matters have become subjects of historical importance in the development of smelter practice.
As has been the case in analogous circumstances elsewhere, when interference with the uncontrolled dispersion of then-considered waste products has often proved of ultimate benefit and a source of much profit to their producers, the enforced treatment of highly sulphurous furnace gases has in several instances resulted in considerable gain to the copper smelters.
Among the methods which are at present economically practicable for dealing with the smelter gases, those of dilution, and of utilisation for acid manufacture are the most important.
The considerations which decide the best course of treatment depend on the numerous economic and local factors which are always of such prime importance in connection with industrial undertakings demanding large capital outlay. The installation of a plant for making sulphuric acid from the gases largely depends on—
(a) For the successful operation of acid-making plant, as at present developed, it is necessary that the proportions of sulphur dioxide in the gases shall not fall below a certain minimum, and further, that the gases shall not contain more than certain limiting proportions of other interfering constituents, such as, for instance, CO2. It is for this reason that the blast furnace operating the true pyritic process furnishes gases of the type most suitable for acid manufacture, since by this process the sulphur-dioxide is obtained in the gases in the most concentrated and the least contaminated form possible under smelting conditions. Even under these circumstances the gases are not in the least of an ideal composition for treatment, owing to their dilution with nitrogen, etc., and the development of the acid-making plants and processes adopted for the successful utilisation of copper blast-furnace gases furnishes a record covering many years of very slow and costly experiment, marked by many preliminary failures and disappointments. These difficulties have now been overcome, as the working of the successful plants attached to both of the Tennessee copper smelters affords conclusive proof, and the sulphur which formerly cost money to dissipate by roasting, now not only acts as fuel, but furnishes a very profitable bye-product.
The requirements for the gases are chiefly the presence of sufficient SO2 and oxygen, and of as little CO2 as possible—factors which depend largely on the proportions of sulphide in the charge. The gas for the acid plant must be supplied in regular and continuous amount, at a specific temperature, and this calls for special care in the smelting operation, furnace manipulation and blast supply, supplementary air admission, etc.
About 3·5 to 4 per cent. of SO2 in the gases delivered at the chambers is the minimum proportion for satisfactory working; CO2 should not exceed about 5 per cent., and about 6·0 per cent. or more of oxygen is also necessary.
(b) In addition to the capital charges involved in the acid-making installation and the costs of adapting the furnace plant and operations to the process, the problem of putting the acid upon the market on a satisfactory economic basis is important, particularly in view of the competition from other sources. The districts which offer a consuming area for the large and regular supply of acid from the smelters are not unlimited in number, and are probably readily accessible to other sources. In view of the costs of production, the distance of the smelter from the market is a serious consideration, since freight charges on sulphuric acid are high, involving special regulations with respect to the form of car and conditions of traffic, and they may readily exceed all possible profits resulting from the sale of the product.
In Tennessee the companies were forced to install acid plants. That at Copperhill is the largest in the world; commenced in 1906, acid manufacture began about two years later, after much experimenting, and further units have gradually been added. The plant now includes two Glover towers, 30 feet across and 50 feet high, 64 cooling chambers about 11 feet × 11 feet × 70 feet high, eight cooling chambers 11 feet × 24 feet × 70 feet high, twelve old chambers 50 feet × 50 feet × 70 feet, six new chambers 50 feet × 50 feet × 75 feet, eight new chambers 23 feet × 50 feet × 80 feet, eight Gay-Lussac towers, with complementary tanks, etc.—producing at the rate of 168,000 tons of 60° B. acid per annum.
The Ducktown Company’s plant was installed in record time, and, like the Copperhill plant, comprises elaborate dust chambers and flues, with Glover and Gay-Lussac towers of special design and construction, and enormous acid-making chambers with complex valves and fittings. The plant is designed to produce about 160 tons of 60° B. acid daily. The analysis of the gases supplied to the towers varied during the early working of the plant; under fairly normal conditions the average analysis of the gases delivered is SO2 3·5 per cent., CO2 3·5 per cent., SO3 trace; the oxygen in the mixture being about 8·0 per cent. The temperature is also apt to vary. Full details on these points are not yet available for general service.
The management of both companies have been successful in obtaining particularly satisfactory contracts for the purchase of their acid by fertiliser corporations.